Article 12 Street worksI1
England, Wales and Scotland
The undertaker may, for the purposes of the authorised development, enter on so much of any of the streets specified in Schedule 3 (streets subject to street works) and may—
break up or open the street, or any sewer, drain or tunnel under it;
tunnel or bore under the street or carry out works to strengthen or repair the carriageway;
remove or use all earth and materials in or under the street;
place and keep apparatus in the street;
maintain, renew or alter apparatus in the street, change its position or remove it;
demolish, remove, replace and relocate any street furniture;
execute any works to provide or improve sight lines;
execute and maintain any works to provide hard and soft landscaping;
carry out re-lining and placement of road markings;
remove and install temporary and permanent signage; and
The powers conferred by paragraph (2) may not be exercised without the consent of the street authority but such consent must not be unreasonably withheld and if the street authority has received an application for consent to exercise powers under paragraph (2) accompanied by all relevant information and fails to notify the undertaker of its decision before the end of the period of 28 days beginning with the date on which the application is submitted with all relevant information, it is deemed to have granted consent.
The undertaker must restore any street that has been temporarily altered under this article to the reasonable satisfaction of the street authority.
Where the undertaker is not the street authority the provisions of sections 54 (advance notice of certain works) to 106 (index of defined expressions) of the 1991 Act apply to any such works.