The North Lincolnshire Green Energy Park Order 2025
S.I. 2025/362 · Made 13 March 2025 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 13th March 2025
Coming into force 4th April 2025
The application was examined by the Examining Authority appointed by the Secretary of State pursuant to Chapter 2 of Part 6 of the 2008 Act and in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3. The Examining Authority has submitted a report to the Secretary of State under section 74(2) of the 2008 Act.
The Secretary of State has considered the report and recommendation of the Examining Authority, has taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f4 and, as a national policy statement has effect in relation to the proposed development, has had regard to the documents and matters referred to in section 104(2) of the 2008 Act.
The Secretary of State, having decided the application, has determined to make an Order giving effect to the proposals comprised in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120, 122, 123 and 140 of the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
2008 c. 29; Parts 1 to 7 were amended by the Localism Act 2011 (c. 20), Chapter 6 of Part 6, and Part 1 of Schedule 13.
- f2
- f3
-
S.I. 2010/103, amended by S.I. 2012/635.
- f4
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- 3Electronic Communications
- Part 2: PRINCIPAL POWERS
- 4Development consent etc. granted by the Order
- 5Limits of deviation
- 6Maintenance of authorised development
- 7Operation of authorised development
- 8Planning permission
- 9Benefit of the Order
- 10Consent to transfer the benefit of the Order
- 11Application and modification of legislative provisions
- Part 3: STREETS
- 12Street works
- 13Power to alter layout, etc., of streets
- 14Permanent stopping up of streets
- 15Temporary stopping up of streets
- 16Public rights of way – creation and temporary stopping up
- 17Accesses
- 18Clearways, prohibitions and restrictions
- 19Classification of highways
- 20Speed limits
- 21Traffic regulation
- 22Agreements with street authorities
- Part 4: COMPULSORY ACQUISITION
- 23Funding
- 24Compulsory acquisition of land
- 25Time limit for exercise of authority to acquire land and rights compulsorily
- 26Compulsory acquisition of rights
- 27Private rights
- 28Application of the 1981 Act
- 29Application of Part 1 of the 1965 Act
- 30Acquisition of subsoil or airspace only
- 31Rights under or over streets
- 32Temporary use of land for carrying out the authorised development
- 33Temporary use of land for maintaining the authorised development
- 34Statutory undertakers
- 35Apparatus and rights of statutory undertakers in stopped up streets
- 36Recovery of costs of new connections
- Part 5: SUPPLEMENTAL POWERS
- 37Discharge of water
- 38Authority to survey and investigate the land
- Part 6: OPERATIONS
- 39Felling or lopping of trees
- 40Removal of hedgerows
- Part 7: MISCELLANEOUS AND GENERAL
- 41Removal of human remains
- 42Protective provisions
- 43Application of landlord and tenant law
- 44Operational land for purposes of the 1990 Act
- 45Defence to proceedings in respect of statutory nuisance
- 46Certification of plans, etc.
- 47Service of notices
- 48Procedure in relation to certain approvals, etc.
- 49Arbitration
- Signature
- Schedule 1: AUTHORISED DEVELOPMENT
- 1AUTHORISED DEVELOPMENT
- 1In the Borough of North Lincolnshire
- Energy park: ERF infrastructure
- 2PARAMETERS TABLE
- Schedule 2: REQUIREMENTS
- Part 1: REQUIREMENTS
- 1Interpretation
- 2Commencement and phasing of the authorised development and notices
- 3Detailed design
- 4Environmental management
- 5Lighting scheme
- 6Landscape design
- 7Landscape and ecology management
- 8Water Resources Assessment
- 9Surface water drainage
- 10Foul water drainage
- 11Construction traffic management and travel planning
- 12Archaeology
- 13Flood risk
- 14Operational travel plan
- 15New highway access
- 16Fuel Type
- 17Decommissioning
- 18Combined heat and power
- 19Commissioning
- 20Carbon Capture
- 21Rail
- 22Local employment and skills
- 23Noise
- 24PRF
- 25Approved details and amendments to them
- 26Amendments agreed by the relevant planning authority
- 27Requirement for written approval
- 28Anticipatory steps towards compliance with any requirement
- Part 2: PROCEDURE FOR DISCHARGE OF REQUIREMENTS
- 29Applications made under requirements
- 30Fees
- 31Further information
- 32Appeals
- 33Interpretation
- Schedule 3STREETS SUBJECT TO STREET WORKS
- Schedule 4STREETS TO BE PERMANENTLY STOPPED UP FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
- Schedule 5: PUBLIC RIGHTS OF WAY
- 1PUBLIC RIGHTS OF WAY TO BE TEMPORARILY SUSPENDED
- 2NEW PUBLIC RIGHTS OF WAY TO BE CREATED
- Schedule 6: PRIVATE MEANS OF ACCESS
- 1PRIVATE MEANS OF ACCESS TO BE CLOSED FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
- 2NEW PRIVATE MEANS OF ACCESS CREATED
- Schedule 7CLEARWAYS
- Schedule 8CLASSIFICATION OF HIGHWAYS
- Schedule 9SPEED LIMITS
- Schedule 10: LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED
- 1OPTION A – LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED
- 2OPTION B - LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED
- Schedule 11: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
- 1Compensation enactments
- 2Compensation enactments
- 3Compensation enactments
- 4Application of the 1965 Act
- 5Application of the 1965 Act
- 6Application of the 1965 Act
- 7Application of the 1965 Act
- 8Application of the 1965 Act
- 9Application of the 1965 Act
- 10Application of the 1965 Act
- Schedule 12: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- 1OPTION A - LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- 2OPTION B - LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 13: REMOVAL OF HEDGEROWS
- 1HEDGEROWS
- 2IMPORTANT HEDGEROWS
- Schedule 14: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- Part 2: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- Part 3: FOR THE PROTECTION OF ANGLIAN WATER SERVICES LIMITED
- 17Application
- 18Interpretation
- 19Apparatus in stopped up streets
- 20Acquisition of land
- 21Removal of apparatus
- 22Facilities and rights for alternative apparatus
- 23Retained apparatus
- 24Expenses and costs
- 25Expenses and costs
- 26Expenses and costs
- 27Cooperation
- 28Unmapped Apparatus
- 29Miscellaneous
- 30Miscellaneous
- 31Disputes
- Part 4: FOR THE PROTECTION OF NORTHERN POWERGRID (YORKSHIRE) PLC
- 32Paragraph 32
- 33Paragraph 33
- 34Paragraph 34
- 35Paragraph 35
- 36Paragraph 36
- 37Paragraph 37
- 38Paragraph 38
- 39Paragraph 39
- 40Paragraph 40
- 41Paragraph 41
- 42Paragraph 42
- 43Paragraph 43
- 44Paragraph 44
- 45Paragraph 45
- Part 5: FOR THE PROTECTION OF RAILWAY INTERESTS
- 46Paragraph 46
- 47Paragraph 47
- 48Paragraph 48
- 49Paragraph 49
- 50Paragraph 50
- 51Paragraph 51
- 52Paragraph 52
- 53Paragraph 53
- 54Paragraph 54
- 55Paragraph 55
- 56Paragraph 56
- 57Paragraph 57
- 58Paragraph 58
- 59Paragraph 59
- 60Paragraph 60
- 61Paragraph 61
- 62Paragraph 62
- 63Paragraph 63
- 64Paragraph 64
- 65Paragraph 65
- 66Paragraph 66
- 67Paragraph 67
- Part 6: FOR THE PROTECTION OF CADENT GAS LIMITED
- Application
- 68Paragraph 68
- Interpretation
- 69Paragraph 69
- On Street apparatus
- 70Paragraph 70
- Apparatus of Cadent in stopped up streets
- 71Paragraph 71
- Acquisition of land
- 72Paragraph 72
- Removal of apparatus
- 73Paragraph 73
- Facilities and rights for alternative apparatus
- 74Paragraph 74
- Retained apparatus: protection of Cadent
- 75Paragraph 75
- Expenses
- 76Paragraph 76
- Indemnity
- 77Paragraph 77
- Enactments and agreements
- 78Paragraph 78
- Co-operation
- 79Paragraph 79
- Access
- 80Paragraph 80
- Arbitration
- 81Paragraph 81
- Notices
- 82Paragraph 82
- Schedule 15DOCUMENTS AND PLANS TO BE CERTIFIED
- Explanatory note