The North London Heat and Power Generating Station (Amendment) Order 2018
S.I. 2018/882 · Made 19 July 2018
Infrastructure Planning
Made 19th July 2018
Coming into force 20th July 2018
An application has been made under paragraph 2 of Schedule 6 to the Planning Act 2008f1 to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f2 for a non-material change to the North London Heat and Power Generating Station Order 2017f3.
The Secretary of State, having considered the application and the responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011, has decided to make this Order amending the North London Heat and Power Generating Station Order 2017.
The Secretary of State, in exercise of the powers conferred by paragraph 2 of Schedule 6 to the Planning Act 2008, makes the following Order:
Annotations to the whole text
Footnotes
- f1
-
2008 c. 29. Paragraph 2 of Schedule 6 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraphs 1 and 72 of Schedule 13 to the Localism Act 2011 (c. 20), and by section 28 of the Infrastructure Act 2015 (c. 7). There are other amendments to the Act that are not relevant to this Order.
- f2
-
S.I. 2011/2055. Regulations 6 and 7 were both amended by SI 2012/635 and S.I. 2015/760.
- f3
-
S.I. 2017/215, as amended by S.I. 2018/822.
Contents
- 1Citation and commencement
- 2Amendment to the North London Heat and Power Generating Station Order 2017
- Signature
- Explanatory note
1Citation and commencement
This Order may be cited as the North London Heat and Power Generating Station (Amendment) Order 2018 and comes into force on 20th July 2018.
2Amendment to the North London Heat and Power Generating Station Order 2017
The North London Heat and Power Generating Station Order 2017 is amended as follows.
In paragraph 1(1) of Schedule 1 (Authorised Development) before “megawatts”, for “70” substitute “78”.
Signature
Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy
Gareth Leigh
Head of Energy Infrastructure Planning
Department for Business, Energy and Industrial Strategy
19th July 2018
Explanatory note
(This note is not part of the Order)
This Order amends the North London Heat and Power Generating Station Order 2017, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order increases the output limit for the generating station from 70 to 78 megawatts of electricity.