Paragraph 3 Stages of the authorised developmentI1

England, Wales and Scotland

No authorised development (except enabling works and the temporary display of site notices and advertisements) is to commence until a written scheme setting out all the stages of construction of the authorised development has been submitted to and approved by the relevant planning authority. Nothing in this Requirement prevents the undertaker from submitting further written schemes revising the approved stages of development for the approval of the relevant planning authority.

Annotations

Commencement

I1

Sch. 2 para. 3 in force at 18.3.2017, see art. 1