Paragraph 10 Construction HoursI1
England, Wales and Scotland
The following operations must only take place between 0900 and 1700 hours Monday to Friday and excluding bank or public holidays—
piling;
excavator and hydraulic jack hammer operations; and
HGV deliveries to and from Broadleys compound.
The following operations may take place outside the core working hours referred to in sub-paragraph (1)—
the installation and removal of protective netting across highways or watercourses;
only at Broadleys compound, the completion of operations commenced during the core working hours which cannot safely be stopped; and
only at Broadleys compound, start up and close down activities up to one hour either side of core working hours.
No artificial lighting is to be used in carrying out the construction of the authorised development other than at Broadleys compound.