Paragraph 13 Construction Environmental Management PlanI1
England, Wales and Scotland
No stage of the authorised development is to commence until, following consultation with NRW, the highways authority and the relevant planning authority, a construction environmental management plan for that stage, which is substantially in accordance with the outline construction environmental management plan, has been submitted to and approved by the relevant planning authority, after consulting with NRW. The construction environmental management plan must include measures to minimise impacts of construction works and must include but not be limited to the following plans—
an ecological management plan including but not limited to method statements for sensitive habitats and species;
hedgerow management plan including but not limited to principles to be followed for hedgerow removal and reinstatement;
a traffic management plan including but not limited to the following—
details of haulage routes for HGVs to use to deliver materials to the authorised development;
communication of the routes to drivers of HGVs;
details of timing for deliveries;
proposals for assessing the existing condition of affected highways; and
details for making good any incidental damage to highways by construction traffic associated with the authorised development.
The authorised development must be carried out in accordance with the construction environmental management plan as approved under this Requirement.
Annotations
Commencement
- I1
Sch. 2 para. 13 in force at 19.8.2016, see art. 1