Part 1 PERMANENT ALTERATION OF LAYOUTI1

England, Wales and Scotland

Table 1

(1)

Area

(2)

Street subject to alteration of layout

(3)

Description of alteration

DenbighshireAccess track from Leger BachModify the existing tarmacked track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points AZ1/AZ2 and BA to provide temporary access to numbered work 1A during construction.
ConwyAccess track from Leger BachModify the existing tarmacked track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points BA to BB to provide temporary access to numbered work 1B during construction.
DenbighshireLon Llewelyn (A453)Extend existing access comprising part of numbered work 4 and shown on the access and rights of way plans (sheet 7) between points AQ1 and AQ2 to provide temporary access to numbered work 4 during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
DenbighshireAccess track from A543 to Broadleys FarmModify the existing track comprising part of numbered works 4 and shown on the access and rights of way plans (sheet 7) between points AQ1/2 and AR to provide temporary access to numbered work 4 during construction.
ConwyHenllan to Llannefydd RoadUpgrade existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BY1 and BY2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
ConwyAccess track from Henllan to Llannefydd RoadModify the existing stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BY1/2 and BZ to provide temporary access to numbered work 1B during construction.
ConwyBontnewydd RoadExtend existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CJ1 and CJ2 to provide temporary access to numbered work 1B during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
ConwyAccess track from Bontnewydd RoadModify the existing stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CJ1/2 and CK to provide temporary access to numbered work 1B during construction.
ConwyHenllan to Llannefydd RoadUpgrade existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 12) between points CN1 and CN2 to provide temporary access to numbered work 1B during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
ConwyAccess track from Henllan to Llannefydd RoadModify the existing stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 12) between points CN1/2 and CQ to provide temporary access to numbered work 1B during construction.

Annotations

Commencement

I1

Sch. 3 Pt. 1 in force at 19.8.2016, see art. 1