OpenLegislation

Paragraph 2 InterpretationI1

England, Wales and Scotland

(1)

The terms used in this Part of this Schedule are as defined in article 2 (interpretation) of this Order save where inconsistent with sub-paragraph (2) which will prevail.

(2)

In this Part of this Schedule—

  • “as built information” means one digital copy of the following information where applicable to the phase in question—

    1. (a)

      as constructed drawings in both PDF and AutoCAD DWG formats for anything designed by the undertaker, in compliance with Interim Advice Note 184 or any successor document;

    2. (b)

      list of suppliers and materials used;

    3. (c)

      product data sheets, technical specifications for all materials used;

    4. (d)

      as constructed information for any utilities discovered or moved during the works;

    5. (e)

      method statements for works carried out;

    6. (f)

      in relation to road lighting, signs and traffic signals, any information required by Series 1300 and 1400 of the Specification for Highway Works;

    7. (g)

      organisation and methods manuals for all products used in the construction of the authorised development;

    8. (h)

      as constructed programme;

    9. (i)

      test results and records as required by the detailed design information and during the construction phase of the project;

    10. (j)

      RSA 3 and exceptions agreed;

    11. (k)

      health and safety file; and

    12. (l)

      other such information as is necessary to enable Highways England to update all relevant databases and to ensure compliance with the Highways England Asset Data Management Manual as in operation at the relevant time including CCTV surveys;

  • “the bond sum” means the sum equal to 120% of the cost of the carrying out of the phase of the HE works concerned (to include all costs including the commuted sum) or such other sum agreed between the undertaker and Highways England;

  • “the cash surety” means the sum of £150,000 or such other sum agreed between the undertaker and Highways England;

  • “county highway works” means those parts of the authorised development to be carried out in the areas identified as Works Nos. 7, 9, 12, 13, 14, 15, 16 and 17 on the works plans, the general arrangement of which is shown on the highway plans and any ancillary works thereto;

  • “commuted sum” means such sum as calculated for each phase as provided for in paragraph 9 of this Part of this Schedule and to be used to fund the future cost of maintaining the HE works;

  • “contractor” means any contractor or sub-contractor appointed by the undertaker to carry out the HE works or any phase of the HE works and approved by Highways England in accordance with paragraph 3(3) of this Part of this Schedule;

  • “detailed design information” means drawings, specifications and calculations as appropriate for the following, and in accordance with the general arrangements of the HE works shown on the highway plans, unless otherwise agreed between Highways England and the undertaker—

    1. (a)

      site clearance details;

    2. (b)

      boundary, environmental and mitigation fencing;

    3. (c)

      road restraints systems and supporting Road Restraint Risk Appraisal Process assessment;

    4. (d)

      drainage and ducting as required by Series 500 of the Specification for Highways Works, HD 43/04, IAN 147/12 and SD 15 Parts 1 – 6 inclusive;

    5. (e)

      earthworks including supporting geotechnical assessments required by HD22/08 and any required Strengthened Earthworks Appraisal Form certification (SEAF);

    6. (f)

      pavement, pavement foundations, kerbs, footways and paved areas;

    7. (g)

      traffic signs and road markings;

    8. (h)

      traffic signal equipment and associated signal phasing and timing detail;

    9. (i)

      road lighting (including columns and brackets);

    10. (j)

      electrical work for road lighting, traffic signs and signals;

    11. (k)

      motorway communications as required by the Designs Manual for Roads and Bridges;

    12. (l)

      highway structures and any required structural approval in principle (AIP);

    13. (m)

      landscaping;

    14. (n)

      agreed departures from the Designs Manual for Roads and Bridges standards;

    15. (o)

      a report of walking, cycling and horse riding carried out in accordance with the Design Manual for Roads and Bridges Standard HD42/17 or any successor document;

    16. (p)

      Stage 2 Road Safety Audit and exceptions agreed and, in the event that any works are not commenced within five years of the date of the Stage 1 Road Safety Audit, a further Stage 1 Road Safety Audit and exceptions agreed;

    17. (q)

      utilities diversions;

    18. (r)

      topographical survey;

    19. (s)

      maintenance and repair strategy in accordance with Designing for Maintenance Interim Advice Note 69/15 or any successor document; and

    20. (t)

      health and safety information including any asbestos survey required by GD05/16 or any successor document,

    where relevant to the phase concerned;

  • “dilapidation survey” means a survey of the condition of the roads, bridges and retaining walls which will be the subject of the physical works comprised in the phase concerned;

  • “estimated costs” means the estimated costs in respect of each phase agreed pursuant to paragraph 5(1)(b) to (d) and (5) of this Part of this Schedule;

  • “the excess” means the amount by which Highways England estimates that the costs referred to in paragraph 5(1)(b) to (d) of this Part of this Schedule will exceed the estimated costs pursuant to paragraph 5(5)(b);

  • “HE works” means those parts of the authorised development to be carried out in the areas identified as Works Nos. 8 and 11 on the works plans, the general arrangement of which is shown on the highway plans, and any ancillary works;

  • “nominated persons” means the undertaker’s representatives or the contractors’ representatives on site during the carrying out of the HE works as notified to Highways England from time to time;

  • “phase” means that part of the HE works which is to be carried out in separate phases in the areas identified as Works Nos. 8 and 11 on the works plans or such other phasing arrangements as agreed with Highways England;

  • “programme of works” means a document setting out the sequence and timetabling of the phase of the HE works in question;

  • “Road Safety Audit” means an audit carried out in accordance with the Road Safety Audit Standard and the approved audit team will include a member of Highways England East Midlands Asset Delivery Road Safety Team;

  • “Road Safety Audit Standard” means the Design Manual for Roads and Bridges Standard HD 19/15 or any successor document;

  • “utilities” means any pipes, wires, cables or equipment belonging to any person or body having power or consent to undertake street works under the 1991 Act; and

  • “winter maintenance” means maintenance of the road surface to deal with snow and ice.

Annotations

Commencement

I1

Sch. 13 Pt. 2 para. 2 in force at 30.10.2019, see art. 1