Paragraph 13 ApprovalsI1

England, Wales and Scotland

(1)

Any approvals, certificates, consents or agreements required or sought from or with the local highway authority pursuant to the provisions of this Part of this Schedule must not be unreasonably withheld or delayed and must be given in writing save that any such approvals, certificates, consents or agreements shall be deemed to have been given if it is neither given nor refused within 42 days of the specified day.

(2)

In this paragraph “specified day” means—

(a)

the day on which particulars of the matter are submitted to the local highway authority under the provisions of this Part of this Schedule; or

(b)

the day on which the undertaker provides the local highway authority with any further particulars of the matter that have been reasonably requested by the local highway authority or within 28 days of the date in paragraph (a),

whichever is the later.

Annotations

Commencement

I1

Sch. 13 Pt. 3 para. 13 in force at 30.10.2019, see art. 1