OpenLegislation

Paragraph 8 Detailed design approvalI1

England, Wales and Scotland

(1)

The details of each component of the authorised development on the main site referred to in requirement 3 (components of development and phasing) must be in accordance with the parameters plan and the principles set out in the design and access statement. The design and access statement can be reviewed and updated by the undertaker in agreement, and in writing, with the relevant planning authority.

(2)

No component of the authorised development on the main site (excluding archaeological investigation, ecological mitigation works and geotechnical or ground contamination investigation) is to commence until the details of that component have been submitted to and approved in writing by the relevant planning authority (following consultation with Northampton Borough Council or any successor authority). The details of each component must include details of the following where they are located within that component—

(a)

rail infrastructure and rail terminal (being Works No.1 and 2);

(b)

embankments and bunds;

(c)

hard landscaping, cycle tracks, footpaths and bridleways;

(d)

surface and foul drainage;

(e)

bicycle, motorcycle and vehicle parking (including (i) the location and quantum of electrical charging points which are to comprise a minimum of 5% of total car parking spaces with passive provision provided for a further 15% of the total car parking spaces and (ii) the location of car parking spaces for those car sharing which are to be at least 8% of the total car parking spaces);

(f)

built development design and layout (including external materials, sustainable energy measures and sprinkler systems in accordance with BSEN;12845:2004 unless otherwise agreed in writing with the relevant planning authority);

(g)

location and quantum of bin stores;

(h)

site levels and finished floor levels;

(i)

estate roads;

(j)

weighbridges;

(k)

gatehouses;

(l)

height barrier at the entrance to the main site restricting HGV right turn movement (including operation and maintenance protocol);

(m)

in respect of the aggregates facility measures to provide for water suppression of stockpiles and wheel washing of vehicles;

(n)

permanent advertisements in the locations identified as S1 and S2 on the parameters plan;

(o)

any temporary means of enclosure;

(p)

any temporary site notices or advertisements;

(q)

fencing walls and other means of enclosure (including acoustic fencing) which must be a maximum height of 3 metres;

(r)

design of access points to public rights of way to deter any unauthorised use;

(s)

location of interpretation boards and litter bins;

(t)

substations; and

(u)

telecommunication masts.

Annotations

Commencement

I1

Sch. 2 Pt. 1 para. 8 in force at 30.10.2019, see art. 1