Article 5 Limits of DeviationI1

England and Wales

In carrying out the authorised development the undertaker may—

(a)

deviate laterally from the lines or situations of the authorised development shown on the works plans to any extent not exceeding 1.0 metres in any direction within the Order limits; and

(b)

deviate vertically from the levels of the authorised development shown on the sections to any extent not exceeding 0.5 metres upwards or downwards.