Paragraph 19 Control of noise during construction of the authorised developmentI1
England and Wales
The authorised development must not commence until a scheme for noise management during the construction of the authorised development has been submitted to and approved by the relevant planning authority.
Taking into account the requirements of chapter 10 of the environmental statement and the CEMP (mitigation items 100 to 116), the scheme for noise management during the construction of the authorised development must set out the particulars of—
the construction of the authorised development and the methods by which it is to be carried out;
the noise attenuation measures to be taken to minimise noise resulting from the construction of the authorised development, including any noise limits; and
the measures for monitoring the noise emitted by the carrying out of the authorised development to ensure compliance with the noise limits and the effectiveness of the attenuation measures.
The authorised development must be undertaken in accordance with the approved noise management scheme.
Annotations
Commencement
- I1
Sch. 2 para. 19 in force at 2.2.2015, see art. 1