Paragraph 27 Site compoundsI1
England and Wales
The authorised development must not commence until details of each site compound, including areas for the storage of materials and machinery, operative parking within the land within the Order limits and proposals and timetables for the restoration of the site compounds upon completion of construction have been submitted to and approved by the relevant planning authority.
Each site compound, storage area and operative parking area must (unless otherwise approved by the relevant planning authority) be provided in accordance with the details approved under paragraph (1) before construction of the link road is commenced and subsequently maintained, reserved and used for their specific purposes for the full duration of the construction of the authorised development. No other part of the land within the Order limits is to be used for any of those purposes.
Site compounds, storage areas and parking areas must be restored in accordance with the approved proposals and timetables unless otherwise approved by the relevant planning authority.
Annotations
Commencement
- I1
Sch. 2 para. 27 in force at 2.2.2015, see art. 1