Paragraph 17 Power to execute worksI1
United Kingdom
If the Licensee fails at any time to perform the obligations arising under clauses 8 or 9 the F1OGA shall be entitled, after giving to the Licensee reasonable notice in writing—
(a)
to execute any works and to provide and install any equipment which in the opinion of the OGA may be necessary to secure the performance of all or any those obligations; and
(b)
to recover the costs and expenses of so doing from the Licensee.
Annotations
Textual amendments
- F1
Word in Sch. substituted (1.10.2016) by The Energy (Transfer of Functions, Consequential Amendments and Revocation) Regulations 2016 (S.I. 2016/912), regs. 1(1), 15(20)
Commencement
- I1
Sch. clause 17 in force at 13.11.2009, see reg. 1