Paragraph 10 I1
Northern Ireland
Where a well operation is to be carried out from a non-production installation or a vessel (not being an installation)—
particulars of—
the meteorological and oceanographic conditions to which that installation or, as the case may be, vessel may foreseeably be subjected;
the depth of water; and
the properties of the seabed and subsoil at the location at which the well operation will be carried out; and
a description of how the well operator and—
the owner of the installation; or
the operator and owner of the vessel,
involved in the well operation will co-ordinate their management systems so as to reduce the risks from a major accident to comply with the relevant statutory provisions.
Annotations
Commencement
- I1
Sch. 10 para. 10 in operation at 19.12.2016, see reg. 1