Regulation 14 Revision of safety case
United Kingdom
In addition to the other occasions on which a duty holder must revise a current safety case pursuant to these Regulations, a duty holder shall revise a current safety case—
when appropriate; and
when directed to do so by the Executive pursuant to regulation 15(1).
Revisions made under sub-paragraph (a) of paragraph (1) which make a material change to the current safety case shall not be effective unless—
the duty holder has sent a version of the current safety case which incorporates the proposed revisions, showing clearly where they are to be made, to the Executive—
at least 3 months, or such shorter period as the Executive may specify; or
where the revisions relate to a combined operation, at least 6 weeks, or such shorter period as the Executive may specify,
before the revisions are to be made; and
the Executive has accepted the revisions.
Without prejudice to the generality of paragraph (2)—
no well operation shall constitute a material change;
no revision prepared or made pursuant to regulation 27 shall constitute a material change;
the movement of a production installation to a new location F1within internal waters to be operated there shall constitute a material change; and
the conversion of a production installation to enable it to be operated as a non-production installation shall constitute a material change,
to the current safety case for the purposes of paragraph (2).