OpenLegislation

Paragraph 16 Fencing and other means of permanent enclosure

Original text. Later amendments are not shown.

(1)

No stage of the onshore transmission works may commence until details of all proposed permanent fences, walls or other means of enclosure of that stage of the onshore transmission works have been submitted to and approved by Lincolnshire County Council in consultation with the relevant planning authority.

(2)

Any permanent fencing and other means of enclosure must be provided and maintained in accordance with the approved details.

(3)

Any approved permanent fencing in relation to the onshore transmission works in Work No. 16 must be completed before those works are brought into use and must be maintained for the operational lifetime of the onshore transmission works in Work No. 16.