Paragraph 18 Operational drainage management and emergency flood response
No part of Work No. 16 may commence until an operational drainage management plan in respect of that part (which accords with the outline operational drainage management plan) and includes provision for the maintenance of any measures identified, has been submitted to and approved by the lead local flood authority, in consultation with the relevant planning authority.
The operational drainage management plan must be implemented as approved.
Work No. 16(a) must not begin operation until an operational emergency flood response plan in respect of Work No. 16 has been submitted to and approved by the lead local flood authority in consultation with the relevant planning authority.
The operational emergency flood response plan must be implemented as approved.