OpenLegislation

Paragraph 54

Original text. Later amendments are not shown.

The undertaker must indemnify the relevant drainage authority in respect of costs, charges and expenses which the relevant drainage authority may reasonably incur by reason of—

(a)

the review, examination or approval of plans under this Part of this Schedule;

(b)

the inspection of the proposed location of the specified work or any protective works and the construction of the specified work or any protective works required by the relevant drainage authority under this Part of this Schedule; or

(c)

the carrying out of any surveys or tests by the relevant drainage authority which are reasonably required in connection with the construction of the specified works and any protective work.