Paragraph 66 Interaction with the Proposed NGET Projects
Without limiting any other provision of this Part of this Schedule, the undertaker must use reasonable endeavours to avoid any conflict arising between the carrying out, maintenance and operation of the authorised development and the Proposed NGET Projects. For the purposes of this paragraph, “reasonable endeavours” means—
undertaking consultation with National Grid Electricity Transmission Plc on detailed design and programming of the authorised works, taking into account such reasonable representations as National Grid Electricity Transmission Plc may provide in relation to proposed plans and timetables;
having regard to the anticipated programme of works for the Proposed NGET Projects and facilitating a co-ordinated approach to construction programming, land assembly, and the carrying out of the authorised works and the Proposed NGET Projects where reasonably possible;
where possible, and subject to National Grid Electricity Transmission Plc having all necessary consents and rights in place, undertaking the placing of ducting or making provision for the Proposed NGET Projects; and
providing a point of contact for continuing liaison and co-ordination throughout the construction and operation of the authorised works.