Paragraph 27
No offshore works within the IDRBNR SAC are to commence until—
the undertaker has received confirmation from Defra or the operator of the Marine Recovery Fund that suitable measures are available to provide the compensation quantum, as determined by the Secretary of State, of 5,760m2 for the impact to the sandbanks which are slightly covered by seawater all the time, feature of the IDRBNR SAC;
the Marine Recovery Fund Payment has been quantified and the undertaker has entered into a contract to make a Marine Recovery Fund Payment;
an implementation and monitoring plan has been submitted to and approved by the Secretary of State; and
the full payment or the first payment in a series of instalments in accordance with the contract under sub-paragraph (b) has been made by the undertaker and the Secretary of State has confirmed in writing that such payment fulfils the requirement for compensation measures under this Part of this Schedule.