Made 17th June 2025

Coming into force 3rd July 2025

The Secretary of State for Transport, makes this Instrument in exercise of the powers conferred by sections 106(3) of the Highways Act 1980f1 (“the Act”) and now vested in the Secretary of Statef2:

In accordance with section 107(1) and (2) of that Act, the Secretary of State has taken into consideration the reasonable requirements of navigation over the waters affected and includes such plans and specifications as necessary.

Annotations to the whole text

Footnotes

f1

1980 c. 66. Section 106(3) is amended by section 1(6) of, and paragraphs 1 and 34(1) and (2) of Schedule 1 to the Infrastructure Act 2015.

f2

S.I. 1981/238.

Contents

  1. 1Section 1
  2. 2Section 2
  3. 3Section 3
  4. Signature
  5. Schedule THE: THE OXFORDSHIRE COUNTY COUNCIL (OXPENS RIVER THAMES PEDESTRIAN/CYCLE BRIDGE) SCHEME 2024
  6. THE HIGHWAYS ACT 1980
  7. Schedule THE SCHEDULE TO THE SCHEMESchedule THE SCHEDULE TO THE SCHEME
  8. Explanatory note

1

This Instrument may be cited as the Oxfordshire County Council (Oxpens River Thames Pedestrian/Cycle Bridge) Scheme 2024 Confirmation Instrument 2025 and shall come into force on the date on which notice that it has been confirmed is first published in accordance with paragraph 1 of Schedule 2 to the Act.

2

The Oxfordshire County Council (Oxpens River Thames Pedestrian/Cycle Bridge) Scheme 2024 (“the Scheme”) is hereby confirmed.

3

The Scheme as confirmed including its Schedule and plans are set out in the Schedule to this Instrument and copies of the Scheme with its accompanying plans are deposited at the offices of the Department for Transport, Deposited Documents Service, MHCLG, 1 Priory Square, Priory Street, Hastings, East Sussex, TN34 1EA and at the offices of Oxfordshire County Council, County Hall, New Road, Oxford, OX1 1ND.

Signature

Signed by Authority of the Secretary of State

Martin Gilmour

A Senior Civil Servant in the Department for Transport

17th June 2025

THE HIGHWAYS ACT 1980

The Oxfordshire County Council (hereinafter referred to as “the County Council”) on its own behalf makes this Scheme in exercise of its powers under Section 106(3) of the Highways Act 1980 and of all other powers enabling them in that behalf.

1

The County Council is authorised to construct over the navigable waters of the River Thames, the bridge specified in the Schedule to this Scheme as part of the highway which they are proposing to construct between the Oxpens Meadow in the north and the Grandpont Nature Park in the south in the City of Oxford, in the County of Oxfordshire.

2

This Scheme may be cited as The Oxfordshire County Council (Oxpens River Thames Pedestrian/Cycle Bridge) Scheme 2024.

Given under the Common Seal
Of the County Council on the 25th day of April 2024
CS
THE COMMON SEAL OF132/24
OXFORDSHIRE COUNTY COUNCIL
was hereunto affixed in the presence of:-
Duly Authorised Officer

Schedule THE SCHEDULE TO THE SCHEME

The location and general design of the Oxpens River Thames Pedestrian/Cycle Bridge are shown on the plans numbered OXPEN-STN-GEN-ALL-RP-S-0101 PO2 and OXPEN-STN-GEN-ALL-RP-S-0102 PO1 annexed hereto.

Explanatory note

(This note is not part of the Instrument)

This Instrument confirms a Scheme to construct a pedestrian/cycle bridge over the navigable waters of the River Thames as part of the highway which Oxfordshire County Council are proposing to construct between Oxpens Meadow in the north and the Grandpont Nature Park in the City of Oxford, in the County of Oxfordshire.