OpenLegislation

The Patents (Amendment No. 3) Rules 1975

S.I. 1975/1021 · Made 23 June 1975

Original text. legislation.gov.uk does not revise statutory instruments, so later amendments are not shown here. Changes made to it are listed under each provision when known.

PATENTS

Made 23rd June 1975

Laid before Parliament 23rd June 1975

Coming into Operation 24th June 1975

The Secretary of State in exercise of powers conferred by section 94 of the Patents Act 1949 and now vested in himf1, and of all other powers enabling him in that behalf, hereby makes the following Rules:—

Annotations to the whole text

Footnotes

f1

S.I. 1970/1537 (1970 III, p. 5293).

Contents

  1. 1Article 1
  2. 2Article 2
  3. 3Article 3
  4. Signature
  5. Explanatory note

1

These Rules may be cited as the Patents (Amendment No. 3) Rules 1975 and shall come into operation on 24th June 1975.

2

The Interpretation Act 1889 shall apply to the interpretation of these Rules as it applies to the interpretation of an Act of Parliament.

3

The following new Rule shall be added to the Patents Rules 1968f1, as amendedf2:—

“158

Notwithstanding the provision for inspection in Rules 38 and 146, the Comptroller may at any time after three months from the date of publication of the complete specification or other document refuse further inspection of any application, specification, drawing or other document in respect of which the Secretary of State has certified that further inspection thereof could in his opinion be prejudicial to the safety of the public;

provided that no such certificate shall be valid for a period in excess of twelve months unless renewed by the Secretary of State. ”

Signature

Stanley Clinton Davis

Parliamentary Under-Secretary of State for Companies, Aviation and Shipping

Department of Trade

23rd June 1975

Explanatory note

These Rules add to the Patents Rules 1968, as amended, a new rule permitting the Comptroller, at any time after three months from the date of publication of the complete specification or other document, to refuse further inspection of any application, specification, drawing or other document in respect of which the Secretary of State has certified that further inspection thereof could in his opinion be prejudicial to the safety of the public.