Paragraph 22 Ministry of DefenceI1
United Kingdom
The Licensee shall give the Ministry of Defence six months' prior notice of any installation movements within the Exploration Area.
The Licensee shall give the Ministry of Defence six weeks' prior notice of any seismic survey within the Exploration Area.
The Licensee shall, at his own expense, install and maintain underwater sonar beacons to Ministry of Defence specifications on any structures that may be temporarily within the Exploration Area, provided that there shall be no requirement to fit such beacons to fixed and charted installations.