The Port Security (Ports of Liverpool and the Manchester Ship Canal) Designation Order 2013 in Wales
S.I. 2013/2181 · Made 2 September 2013
Merchant Shipping
Maritime Security
Made 2nd September 2013
Laid before Parliament 5th September 2013
Coming into force 3rd October 2013
The Secretary of State for Transport makes this Order in exercise of the powers conferred by section 2(2) of the European Communities Act 1972f1.
The Secretary of State is a Minister designated for the purposes of section 2(2) of the European Communities Act 1972 in relation to port security, measures relating to the safety of ships and the health and safety of persons on them, and maritime transportf2.
Annotations to the whole text
Footnotes
- f1
-
1972 c.68; section 2(2) was amended by section 27(1)(a) of the Legislative and Regulatory Reform Act 2006 (c.51) and by Part 1 of the Schedule to the European Union (Amendment) Act 2008 (c.7).
- f2
-
S.I. 1993/595, 1994/757 and 2004/706.
Contents
- 1Citation and commencement
- 2Port boundary: Liverpool
- 3Port boundary: the Manchester Ship Canal
- 4The Liverpool and Manchester Ship Canal Port Security Authority Limited
- 5Review
- Signature
- Schedule 1
- 1Boundary of the Port of Liverpool
- 2Inset Plan A–Liverpool
- Inset Plan B–Birkenhead
- Inset Plan C–Tranmere Oil Terminal
- 3Seaward limits of the boundary of the Port of Liverpool
- Schedule 2: Parts of the boundary of the Port of the Manchester Ship Canal
- Eastham Locks
- Partington Basin North and Partington Jetty
- Stanlow Oil Terminal
- Explanatory note
1Citation and commencement
This Order may be cited as the Port Security (Ports of Liverpool and the Manchester Ship Canal) Designation Order 2013 and comes into force on 3rd October 2013.
2Port boundary: Liverpool
For the purposes of regulation 3(2)(a) of the Port Security Regulations 2009f1, the boundary of the Port of Liverpool is identified as follows.
The boundary is generally shown by the inner edge of the red line on the plan in Part 1 of Schedule 1.
As to the inland limits of the boundary—
the boundary, so far as not included in the rectangles referred to in paragraph (4), runs along the beaches and foreshores on either side of the River Mersey up to Warrington Bridge; and
the boundary crosses the river along the seaward edge of Warrington Bridge.
As to the parts of the boundary included in the rectangles edged in black and marked “A”, “B” and “C” on the plan in Part 1 of Schedule 1, the boundary is more particularly shown by the seaward edges of the red lines on each of the corresponding inset plans, in Part 2 of Schedule 1, headed respectively “Inset Plan A–Liverpool”, “Inset Plan B–Birkenhead” and “Inset Plan C–Tranmere Oil Terminal”.
As to the seaward limits of the boundary, the boundary is more particularly shown by the lines drawn between the co-ordinates on the plan in Part 3 of Schedule 1.
Where the red line runs along a beach or foreshore, the boundary runs along the edge of the land on that beach or foreshore which is below the level of mean high water springs.
3Port boundary: the Manchester Ship Canal
For the purposes of regulation 3(2)(a) of the Port Security Regulations 2009, the boundary of the Port of the Manchester Ship Canal is the same as the boundary of the Manchester Ship Canal, except that, for the areas shown on the plans headed—
“Eastham Locks”,
“Partington Basin North and Partington Jetty”, and
“Stanlow Oil Terminal”,
in Schedule 2, the boundary is shown by the waterward edges of the red lines on each of those plans.
4The Liverpool and Manchester Ship Canal Port Security Authority Limited
For the purposes of the Port Security Regulations 2009, The Liverpool and Manchester Ship Canal Port Security Authority Limited (company number 08652323), a company limited by guarantee (“the Authority”), is designated as the port security authority for the ports of Liverpool and the Manchester Ship Canal.
The Authority is not to be regarded as the servant or agent of the Crown or as enjoying any status, immunity or privilege of the Crown and its property is not to be regarded as property of, or held on behalf of, the Crown.
5Review
The Secretary of State must from time to time—
carry out a review of this Order,
set out the conclusions of the review in a report, and
publish the report.
In carrying out the review the Secretary of State must, so far as is reasonable, have regard to how Directive 2005/65/EC of the European Parliament and of the Council of 26th October 2005 (which is implemented by means of the Port Security Regulations 2009f1) is implemented in other member States.
The report must in particular—
set out the objectives intended to be achieved by the regulatory system established by those Regulations and this Order,
assess the extent to which those objectives are achieved, and
assess whether those objectives remain appropriate and, if so, the extent to which they could be achieved with a system that imposes less regulation.
The first report under this article must be published before 3rd October 2018.
Reports under this article are afterwards to be published at intervals not exceeding five years.
Signature
Signed by authority of the Secretary of State for Transport
Stephen Hammond
Parliamentary Under Secretary of State
Department for Transport
2nd September 2013
1Boundary of the Port of Liverpool
2Inset Plan A–Liverpool
Inset Plan B–Birkenhead
Inset Plan C–Tranmere Oil Terminal
3Seaward limits of the boundary of the Port of Liverpool
Eastham Locks
Partington Basin North and Partington Jetty
Stanlow Oil Terminal
Explanatory note
(This note is not part of the Order)
This Order is one of a series of Orders implementing Directive 2005/65/EC of the European Parliament and of the Council of 26th October 2005 (OJ L 310, 25.11.2005, p28-39) on enhancing port security at individual ports in the United Kingdom. The Directive was transposed in relation to the United Kingdom as a whole by the Port Security Regulations 2009 (S.I. 2009/2048).
Article 2 and Schedule 1 identify the boundary of the Port of Liverpool for the purposes of regulation 3(2)(a) of the Port Security Regulations 2009. Article 3 and Schedule 2 identify the boundary of the Port of the Manchester Ship Canal for the purposes of that regulation 3(2)(a). Article 4(1) designates The Liverpool and Manchester Ship Canal Port Security Authority Limited, for the purposes of regulation 5 of those Regulations, as the port security authority for the Ports of Liverpool and the Manchester Ship Canal. Article 4(2) makes provision with respect to the Authority’s status as a non-Crown body. Article 5 requires the Secretary of State to review the operation and effect of this Order and publish a report before 3rd October 2018 and within every five years after that. Following a review it will fall to the Secretary of State to consider whether the Order should remain as it is, or be revoked or be amended. A further instrument would be needed to revoke the Order or to amend it.
A full impact assessment of the effect that this instrument will have on the costs of business and the voluntary sector is available from Gary Kemp at Zone 2/32, 33 Horseferry Road, London SW1P 4DR (Tel: 020 7944 6242; email: [email protected] and is published with the Explanatory Memorandum alongside the instrument on http://www.legislation.gov.uk .