Paragraph 14 Control of noise during operational phaseI1
England, Wales and Scotland
The undertaker must not commence commissioning of any stage of the authorised development until a written scheme for the management of noise generated by the operation of that stage of the authorised development has been submitted to and approved by the relevant planning authority.
The scheme to be submitted and approved under sub-paragraph (1) must be substantially in accordance with section 8.7 of the environmental statement and must include details of—
the noise attenuation measures to be taken to minimise operational noise, including any noise limits;
noise monitoring requirements including the location of monitoring equipment; and
the measures to be taken, including timescales, to address any noise issues identified.
The noise management scheme must be implemented as approved and maintained for the duration of the operation of the relevant stage of the authorised development.