Paragraph 5 Removal of apparatusI1
England, Wales and Scotland
If, in accordance with the agreement reached under paragraph 4 or in any other authorised manner, the undertaker acquires an interest in any land in which any apparatus is placed—
the apparatus must not be removed under this Part; and
any right of National Grid to maintain the apparatus in the land must not be extinguished,
until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of National Grid in accordance with sub-paragraphs (2) to (5).
If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in the land, it must give to National Grid at least 56 days’ advance written notice of that requirement, together with a plan of the work proposed and of the proposed position of the alternative apparatus to be provided or constructed; and in that case (or if, in consequence of the exercise of any power conferred by this Order, National Grid reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to National Grid to its satisfaction (taking into account paragraph 6(1)) the necessary facilities and rights for—
the construction of alternative apparatus in other land of the undertaker; and
subsequently for the maintenance of that apparatus.
If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed, National Grid must, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances to endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed, except that the obligation in this sub-paragraph does not require National Grid to use its compulsory purchase powers for this purpose unless it elects to so do.
Any alternative apparatus to be constructed in land of the undertaker under this Part must be constructed in such manner and in such line or situation as may be agreed between National Grid and the undertaker.
National Grid must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the grant to National Grid of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under this Part.