Paragraph 11 IndemnityI1
England, Wales and Scotland
Subject to sub-paragraphs (3) to (5), the undertaker must indemnify DCC and hold it harmless against all claims, demands, costs, damages, expenses, penalties and losses that DCC may have, sustain or become liable for in consequence of works under paragraph 6(1) in respect of—
the commencement, carrying out, execution or retention of the works;
any breach of this Part relating to the performance of the works caused by the actions or default of the undertaker, its contractors, sub-contractors, licensees, agents and invitees;
damage to the environment caused by the undertaker during the works including but not limited to pollution or contamination; and
any breach of any stipulation or otherwise of any deeds of grant (or any renewal of any of the deeds of grant made on substantially the same terms, provided that DCC has supplied the undertaker with a copy of the new document) arising from the works.
The indemnity in sub-paragraph (1) includes, without limitation, the costs reasonably incurred by DCC in making good damage to DCC apparatus or restoring an interruption in the supply provided by DCC.
Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of DCC, its officers, servants, contractors or agents.
DCC must give the undertaker reasonable notice of any claim or demand; and no settlement or compromise may be made without the consent of the undertaker.
DCC must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands and penalties to which the indemnity in sub-paragraph (1) applies and, if requested to do so by the undertaker, DCC must provide an explanation of how the claim has been minimised.
The undertaker is liable under this paragraph only for claims reasonably incurred by DCC.
Annotations
Commencement
- I1
Sch. 4 Pt. 4 para. 11 in force at 30.12.2015, see art. 1