Paragraph 3 Further informationI1
England, Wales and Scotland
In relation to any application referred to in paragraph 2(1), the relevant planning authority may request such further information from the undertaker as is necessary to enable it to consider the application.
If the relevant planning authority considers that further information is necessary, the relevant planning authority must, within 21 business days of receipt of the application, notify the undertaker in writing specifying the further information required and (if applicable) to which part of the application it relates.
If the requirement specifies that consultation with a requirement consultee is required, the relevant planning authority must—
issue the consultation to the requirement consultee within 2 business days of receipt of the application; and
notify the undertaker in writing specifying any further information requested by the requirement consultee within 2 business days of receipt of such a request and in any event within 21 business days of receipt of the application.