Article 6 Planning permissionI1
England and Wales
If planning permission is granted under the powers conferred by the 1990 Act for development any part of which is within the Order limits following the coming into force of this Order that is—
not itself a nationally significant infrastructure project under the 2008 Act or part of such a project; or
required to complete or enable the use or operation of any part of the development authorised by this Order,
then the carrying out, use or operation of such development under the terms of the planning permission does not constitute a breach of the terms of this Order.
The provisions of this Order do not preclude or apply to any development, or any part of a development, which is carried out by, or used by, Network Rail on any land (whether or not within the Order limits)—
that is or will become operational railway land and is carried out in accordance with any planning permission granted under the 1990 Act including a planning permission granted under article 3 and Class A of Part 8 of Schedule 2 to the Town and Country Planning (General Permitted Development) (England) Order 2015f1; or
that is carried out in accordance with any planning permission granted under the 1990 Act including a planning permission granted under article 3 and Class A of Part 18 of Schedule 2 to that Order.
Annotations
Commencement
- I1
Art. 6 in force at 5.12.2022, see art. 1
Footnotes
- f1