Paragraph 93 I1

(1)

The undertaker and National Grid will co-operate and work together to secure that the works proposed to be carried out by National Grid under the powers of the 2016 Order and the authorised works to be carried out by the undertaker under this Order will so far as reasonably possible be programmed, and arrangements for the carrying out, use and maintenance of those works will be made, so as, so far as reasonably possible, to avoid undue delay or any conflict arising between the carrying out, use and maintenance of those proposed works and carrying out, use and maintenance of the authorised development.

(2)

Any consent, agreement or approval by National Grid or the undertaker under this Part of this Schedule must not be unreasonably withheld or delayed.