Work Nos. 26, 26A and 26B must not commence until a flood plan which details—
the emergency and evacuation procedures for use of the temporary and permanent compound;
the location, height above ground level and the duration on site of the welfare facility on the temporary compound; and
the means to remove materials stored at the temporary and permanent compound in the event of flooding,
has been submitted to and approved in writing by the relevant planning authority in consultation with the Environment Agency and the relevant lead local flood authority. The approved flood plan must thereafter be complied with to the satisfaction of the relevant planning authority.
The landscaping and planting forming part of Work No. 26 must be carried out in accordance with the relevant design drawing prior to first use of Work No. 26 as a permanent maintenance compound. Any tree or shrub planted as part of the landscaping that, within a period of five years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless the relevant planning authority gives written consent to any variation.
Prior to the first use of Work No. 26 as a permanent maintenance compound either—
the Clanage Road compound, landscaping and access plan (Plan ref: 46470.BQ.04.20-261 rev T) must be redrawn to show the proposed levels for the flood compensation mitigation area to be 7.3m AOD; or
details of an on-site flood storage scheme or other works to provide adequate flood compensation mitigation,
must be submitted to the relevant planning authority for approval in consultation with the Environment Agency. The mitigation area must be carried out in accordance with the approved details and maintained thereafter.
Prior to the first use of Work No. 26 as a permanent maintenance compound details of the permanent paladin type fencing including colour height and location must be submitted to and approved by the relevant planning authority and once installed must be permanently maintained.
In this requirement “AOD” means above ordnance datum.