Schedule 1 SCHEDULED WORKS
In the City of Portsmouth–
-
Work No 1. Piled suspended deck over area shown shaded on drawing 97.100.024 C (sheet 2 of 2) together with a link connecting the suspended decking to the Wightlink Pedestrian Jetty together with buildings and other structures for commercial and leisure purposes situated upon the said piled deck.
-
Work No 2. Replacement quay walls between chainage 221 metres and chainage 320 metres.
-
Work No 3. Replacement quay walls between chainage 199 metres and chainage 70 metres together with demolition of the Marlborough Pier.
-
Work No 4. Cofferdam wall across Vernon Creek between chainage 199 metres and 221 metres.
-
Work No 5. Cantilevered belvedere and replacement quays between chainage 70 metres and 10 metres—existing sea wall to remain exposed over this length.
-
Work No 6. Replacement quay walls between chainage 10 metres and chainage—30 metres.