The Progress Power (Gas Fired Power Station) (Amendment) Order 2020

S.I. 2020/807 · Made 27 July 2020

Original text. legislation.gov.uk does not revise statutory instruments, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Infrastructure Planning

Made 27th July 2020

Coming into force 28th July 2020

An Application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008f1, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f2 for non-material changes to the Progress Power (Gas Fired Power Station) Order 2015f3.

The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011, has decided to make the changes on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.

Accordingly, the Secretary of State, in exercise of the powers conferred by paragraphs 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order—

Annotations to the whole text

Footnotes

f1

2008 c. 29. Paragraph 2 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraphs 1 and 72 of Schedule 13 and Schedule 25(20) of the Localism Act 2011 (c. 20), and by section 28 of the Infrastructure Act 2015 (c. 7).

f2

S.I. 2011/2055. Relevant amendments to this instrument were made by S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2015/760, S.I. 2017/314, S.I. 2017/524, S.I. 2018/378 and S.I. 2019/734.

f3

S.I. 2015/1570, to which there are amendments not relevant to this Order.

Contents

  1. 1Citation and commencement
  2. 2Amendment to the Progress Power (Gas Fired Power Station) Order 2015
  3. 3Amendments to Schedule 2 (requirements)
  4. Signature
  5. Explanatory note

1Citation and commencement

This Order may be cited as the Progress Power (Gas Fired Power Station) (Amendment) Order 2020 and comes into force on 28th July 2020.

2Amendment to the Progress Power (Gas Fired Power Station) Order 2015

The Progress Power (Gas Fired Power Station) Order 2015 (“the 2015 Order”) is amended in accordance with this Order.

3Amendments to Schedule 2 (requirements)

For paragraph 1 of Schedule 2 to the 2015 Order substitute “The authorised development must commence no later than 13th August 2021.”.

Signature

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Gareth Leigh

Head of Energy Infrastructure Planning

Department for Business, Energy and Industrial Strategy

27th July 2020

Explanatory note

(This note is not part of the Order)

This Order amends the Progress Power (Gas Fired Power Station) Order 2015, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material amendment under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order amends the time limit within which the development authorised by the Order must be commenced.