Paragraph 9 F1

England, Wales and Scotland

As regards temporary restrictions of the capacity of railway lines, for reasons such as infrastructure works, including associated speed restrictions, axle load, train length, traction, or structure gauge (‘capacity restrictions’), of a duration of more than seven consecutive days and for which more than 30% of the estimated traffic volume on a railway line per day is cancelled, re-routed or replaced by other modes of transport, the infrastructure managers concerned must publish all capacity restrictions and the preliminary results of a consultation with the applicants for a first time at least 24 months, to the extent they are known, and, in an updated form, for a second time at least 12 months before the change of the working timetable concerned.