Paragraph 33 F1
When freight wagons start operations, the organisation must have procedures to—
obtain the initial documentation and to collect sufficient information on planned operations;
analyse the initial documentation and to provide the first maintenance file, also taking into account the obligations contained in any associated guarantees;
ensure that the implementation of the first maintenance file is done correctly.
Annotations
Textual amendments
- F1
Schs. 8-11 inserted (31.12.2020) by The Rail Safety (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/837), reg. 1, Sch. para. 1 (as amended in Sch. 11 paras. 14, 16, 17 by S.I. 2019/1310, reg. 1(2)(c), Sch. 1 paras. 2, 3, 4); 2020 c. 1, Sch. 5 para. 1(1)
Notes on Schedule 10
Marginal citations
- M1
Annexes IV and V of Commission Regulation (EU) No 445/2011 are substantially reproduced in Schedule 9.