Paragraph 14 Offshore safety managementI1

England, Wales and Scotland

No part of the authorised scheme may commence until the MMO, following consultation with the MCA, has confirmed in writing that the undertaker has taken into account and, so far as is applicable to that part of the authorised scheme, adequately addressed all MCA recommendations as appropriate to the authorised scheme contained within MGN654 “Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues” and its annexes.

Annotations

Commencement

I1

Sch. 11 para. 14 in force at 28.4.2025, see art. 1