Paragraph 21 Updating of cable monitoring planI1

England, Wales and Scotland As made

Following installation of array cables, the cable monitoring plan required under condition 11(1)(n)(v) must be updated with the results of the post-installation surveys. The plan must be implemented during the operational lifetime of the project and reviewed as specified within the plan, following cable burial surveys, or as instructed in writing by the MMO.