OpenLegislation

Paragraph 17 I1

England, Wales and Scotland

The undertaker must implement the measures set out in the Final GCIMP approved by the Secretary of State, unless otherwise agreed by the Secretary of State following consultation with the relevant statutory nature conservation body, and the local planning authority for the area in which the onshore guillemot compensation measure is to be provided. No operation of any wind turbine generator forming part of the authorised development may begin until the Final GCIMP has been implemented and this has been confirmed to the Secretary of State.

Annotations

Commencement

I1

Sch. 17 para. 17 in force at 28.4.2025, see art. 1