Paragraph
Work No. 2 the construction and installation and keeping of a 132kV underground cable and fibre optic cable 1.2km in length from Oswestry substation connecting to Work No.3 at a terminal structure at Long Wood (grid reference: SJ 3113229877) comprising three 132kV single core cables together with a fibre optic cable installed in 200mm diameter polyethylene ducts laid in trefoil formation together with the installation of cable protection tiles above at a depth of approximately 1.4m to ensure a final minimum depth of 975mm and as shown on sheet 1 of the works plans; and
site preparation works and site clearance (including fencing, felling and vegetation removal);
earthworks (including soil stripping and storage and site levelling);
carrying out surveys or taking soil samples;
establishment of temporary laydown and storage areas, temporary vehicle parking and construction fencing;
cutting down, uprooting, topping or lopping of trees or shrubs or cutting back their roots;
reinstatement hedgerow planting;
establishment of temporary means of access and trackways;
drainage works;
ramps, means of access, footpaths and bridleways;
works to alter the position of apparatus, including mains, sewers, drains and cables;
works to alter the course of, or otherwise interfere with a watercourse;
works to mitigate any adverse effects of the construction, maintenance or operation of the authorised development;
works for the benefit or protection of land affected by the authorised development;
the removal, disposal or re-siting of apparatus;
open trench excavations and directional drilling.
Notes on Schedule 1
Commencement
- I1
Sch. 1 in force at 14.4.2020, see art. 1