Work No. 2 the construction and installation and keeping of a 132kV underground cable and fibre optic cable 1.2km in length from Oswestry substation connecting to Work No.3 at a terminal structure at Long Wood (grid reference: SJ 3113229877) comprising three 132kV single core cables together with a fibre optic cable installed in 200mm diameter polyethylene ducts laid in trefoil formation together with the installation of cable protection tiles above at a depth of approximately 1.4m to ensure a final minimum depth of 975mm and as shown on sheet 1 of the works plans; and

(a)

site preparation works and site clearance (including fencing, felling and vegetation removal);

(b)

earthworks (including soil stripping and storage and site levelling);

(c)

carrying out surveys or taking soil samples;

(d)

establishment of temporary laydown and storage areas, temporary vehicle parking and construction fencing;

(e)

cutting down, uprooting, topping or lopping of trees or shrubs or cutting back their roots;

(f)

reinstatement hedgerow planting;

(g)

establishment of temporary means of access and trackways;

(h)

drainage works;

(i)

ramps, means of access, footpaths and bridleways;

(j)

works to alter the position of apparatus, including mains, sewers, drains and cables;

(k)

works to alter the course of, or otherwise interfere with a watercourse;

(l)

works to mitigate any adverse effects of the construction, maintenance or operation of the authorised development;

(m)

works for the benefit or protection of land affected by the authorised development;

(n)

the removal, disposal or re-siting of apparatus;

(o)

open trench excavations and directional drilling.