Work No.5 —Works at Wem substation as shown on sheet 16 of the works plans comprising the installation of a 132kV gantry, isolator, associated busbar, a 132kV to 33kV transformer, 33kV cable and a 33kV circuit breaker and—

(a)

site preparation works and site clearance (including fencing);

(b)

levelling;

(c)

creation of hard stoned area.