Paragraph 10 Approved plans and amendments to approved plansF1I1
England and Wales
Where a requirement requires the authorised development to be carried out in accordance with a plan, scheme, statement, strategy or details (the “plan”) approved by the relevant planning authority, the plan must be taken to include any amendments that may be approved subsequently by the relevant planning authority (after consulting every person required to be consulted before approval of the original plan).
The relevant planning authority must not approve the plan or an amendment to the plan unless it is satisfied that the plan or the amendment is unlikely to give rise to any new or materially different environmental effects from those assessed in the environmental statement.
Annotations
Textual amendments
- F1
Sch. 2 requirement. 10 heading substituted (29.9.2020) by virtue of The Reinforcement to the North Shropshire Electricity Distribution Network (Correction) Order 2020 (S.I. 2020/1053), art. 1, Sch.
Commencement
- I1
Sch. 2 para. 10 in force at 14.4.2020, see art. 1