OpenLegislation

Regulation 17 Amendment to regulation 8 (certification requirements)I1

England, Wales and Scotland

For regulation 8(1)(b) substitute—

“(b)

a scheme where—

(i)

installers are certified to that scheme’s standards by a certification body or organisation accredited to EN 45011 or EN ISO/IEC 17065:2012;

(ii)

the plant is installed in accordance with the installation requirements applicable to the plant under that scheme on the plant’s first commissioning date and which are equivalent to a relevant installation standard; and

(iii)

that scheme is equivalent to the Microgeneration Certification Scheme.”.

Annotations

Commencement

I1

Reg. 17 in force at 24.3.2016, see reg. 1