OpenLegislation

Article 8 Small onshore wind generating stations accredited, or additional capacity added, between 1stApril2017 and 31stMarch 2018: investment freezing condition met

Original text. Later amendments are not shown.

(1)

The circumstances set out in this Article are where the electricity is—

(a)

generated using the original capacity of a small onshore wind generating station—

(i)

which was accredited during the period beginning with 1st April 2017 and ending with 31st March 2018, and

(ii)

in respect of which both the approved development condition and the investment freezing condition are met, or

(b)

generating using additional capacity of a small onshore wind generating station, where—

(i)

the station was accredited on or before 30th June 2016,

(ii)

in the Authority’s view, the additional capacity first formed part of the station during the period beginning with 1st April 2017 and ending with 31st March 2018, and

(iii)

both the approved development condition and the investment freezing condition are met in respect of the additional capacity.