Paragraph 4 Capped generating stations in the 2019/20 obligation period and subsequent obligation periodsF1
(1)
This paragraph applies to a generating station that is a capped generating station on qualification day in any obligation period (the “previous obligation period”) beginning with the 2018/19 obligation period.
(2)
No more than A x 125,000 ROCs may be issued in respect of relevant electricity generated by the generating station during the next obligation period after the previous obligation period.
(3)
In sub-paragraph (2), A is the number of capped combustion units included in the generating station on qualification day in the previous obligation period.
Annotations
Textual amendments
- F1
Sch. 6 inserted (20.7.2018) by The Renewables Obligation (Amendment) Order 2018 (S.I. 2018/896), arts. 1(1), 6