Article 25 The amount of electricity to be stated in each NIROCI1
Northern Ireland
Each NIROC is to state the amount of electricity in respect of which it has been issued.
The amount of electricity to be stated in each NIROC depends on—
the way in which the electricity in respect of which it is to be issued has been generated, and
the type of generating capacity used to generate the electricity in respect of which the NIROC is to be issued.
Subject to Articles 26 to 30, the amount of electricity to be stated in each NIROC is to be determined in accordance with paragraphs (4) to (10).
Each NIROC to be issued in respect of electricity generated—
using 2013/14 capacity, and
in a way described in the first column of Part 2A of Schedule 2,
must state the amount of electricity which corresponds to that description in the second column of that Part of that Schedule.
Each NIROC to be issued in respect of electricity generated—
using 2013/14 capacity, and
in a way described in the first column of Part 2A of Schedule 2,
must state the amount of electricity which corresponds to that description in the second column of that Part of that Schedule.
Each NIROC to be issued in respect of electricity generated—
using 2014/15 capacity, and
in a way described in the first column of Part 2A of Schedule 2,
must state the amount of electricity which corresponds to that description in the third column of that Part of that Schedule.
Each NIROC to be issued in respect of electricity generated—
using 2015/16 capacity, and
in a way described in the first column of Part 2B of Schedule 2,
must state the amount of electricity which corresponds to that description in the second column of that Part of that Schedule.
Each NIROC to be issued in respect of electricity generated—
using post-2016 capacity, and
in a way described in the first column of Part 2B of Schedule 2,
must state the amount of electricity which corresponds to that description in the third column of that Part of that Schedule.
The amount of electricity to be stated in each NIROC to be issued in respect of electricity generated—
using pre–2013 capacity, and
in a way which is not described in the first column of Part 2 of Schedule 2,
is 1 megawatt hour.
The amount of electricity to be stated in each NIROC to be issued in respect of electricity generated—
using 2013/14 capacity, 2014/15 capacity, 2015/16 capacity or post-2016 capacity, and
in a way which is not described in the first column of Part 2A or Part 2B of Schedule 2,
is 1 megawatt hour.
Annotations
Textual amendments
- F1
Art. 25(2)-(10) substituted for Art. 25(2)-(5) (1.5.2013) by The Renewables Obligation (Amendment) Order (Northern Ireland) 2013 (S.R. 2013/116), arts. 1(1), 13 (with art. 34)
Commencement
- I1
Art. 25 in operation at 1.4.2009, see art. 1