Article 26A High-range co-firing in the 2013/14 obligation periodF1

(1)

This Article applies to electricity which is generated—

(a)

before 1st April 2014,

(b)

in the way described as “high-range co-firing” in Schedule 2, and

(c)

by a generating station to which Article 27 does not apply.

(2)

Subject to paragraph (4), the amount of electricity to be stated in each NIROC issued in respect of electricity to which this Article applies is 107 of a megawatt hour.

(3)

Paragraph (4) applies to electricity to which this Article applies which is generated—

(a)

in the way described as “high-range co-firing with CHP” in Schedule 2, and

(b)

using—

(i)

pre-2013 capacity, or

(ii)

2013/15 capacity in respect of which a declaration has been made in accordance with Article 26(8).

(4)

Where this paragraph applies, the amount of electricity to be stated in each NIROC is—

(a)

in respect of the qualifying proportion of the electricity to which this paragraph applies, 56 of a megawatt hour; and

(b)

in respect of the remainder of the electricity to which this paragraph applies, 107 of a megawatt hour.

(5)

This Article is subject to Article 30.

Annotations

Textual amendments

F1

Arts. 26A-26E inserted (1.5.2013) by The Renewables Obligation (Amendment) Order (Northern Ireland) 2013 (S.R. 2013/116), arts. 1(1), 15 (with art. 34)