Article 27 Microgenerators and qualifying new small scale generatorsF1
Northern Ireland
This Article applies to a generating station which—
is an accredited microgenerator,
has not had a total declared net capacity in excess of 50 kilowatts at any time after 31st March 2009, and
is not a qualifying new onshore wind station or a qualifying new hydro station or a qualifying new solar photovoltaic station or a qualifying new anaerobic digestion station.
The amount of electricity to be stated in each NIROC issued in respect of electricity generated—
by a generating station to which this Article applies, and
using—
pre-2013 capacity, or
2013/14 capacity, or
2014/15 capacity,
is of a megawatt hour.
The amount of electricity to be stated in each NIROC issued in respect of electricity generated—
by a generating station to which this Article applies, and
using 2015/16 capacity,
is of a megawatt hour.
The amount of electricity to be stated in each NIROC issued in respect of electricity generated—
by a generating station to which this Article applies, and
using post-2016 capacity,
is of a megawatt hour.
In this Article and in Articles 27A to 27C—
“2010/2015 qualifying new solar photovoltaic station” means a generating station which—
- (a)
generates electricity from the direct conversion of sunlight to electricity,
- (b)
was accredited after 31st March 2010 and before 1st October 2015, and
- (c)
has not had a declared net capacity in excess of 250 kilowatts at any time after 31st March 2010;
- (a)
“2015/2016 qualifying new solar photovoltaic station” means a generating station which—
- (a)
generates electricity from the direct conversion of sunlight to electricity,
- (b)
was accredited after 30th September 2015 and before 1st October 2016, and
- (c)
has not had a declared net capacity in excess of 250 kilowatts at any time after 30th September 2015;
- (a)
“2016/2017 qualifying new solar photovoltaic station” means a generating station which—
- (a)
generates electricity from the direct conversion of sunlight to electricity,
- (b)
was accredited after 30th September 2016, and
- (c)
has not had a declared net capacity in excess of 250 kilowatts at any time after 30th September 2016;
- (a)
“qualifying new hydro station” means a hydro generating station which—
- (a)
was first accredited after 31st March 2010, and
- (b)
has not had a declared net capacity in excess of 5 megawatts at any time after 31st March 2010;
- (a)
“qualifying new onshore wind station” means a generating station which—
- (a)
generates electricity from onshore wind,
- (b)
was accredited after 31st March 2010, and
- (c)
has not had a declared net capacity in excess of 5 megawatts at any time after 31st March 2010;
- (a)
“qualifying new solar photovoltaic station” means—
- (a)
a 2010/2015 qualifying new solar photovoltaic station,
- (b)
a 2015/2016 qualifying new solar photovoltaic station, and
- (c)
a 2016/2017 qualifying new solar photovoltaic station;
- (a)
“qualifying new anaerobic digestion station”, means a generating station which—
- (a)
generates electricity from gas formed by the anaerobic digestion of material which is neither sewage nor material in a landfill,
- (b)
was first accredited after 31st March 2011, and
- (c)
has not had a declared net capacity in excess of 5 megawatts at any time after 31st March 2011.
- (a)
This Article is subject to Article 30.
Annotations
Textual amendments
- F1
Art. 27 substituted (1.7.2015) by The Renewables Obligation (Amendment) Order (Northern Ireland) 2015 (S.R. 2015/287), arts. 1(1), 2 (with art. 4)