Schedule 6 DirectionsI1
England and Wales
The italicised letters in the forms of directions in this Schedule indicate the information to be included as follows—
name of engineer;
address of engineer;
name of panel to which engineer is appointed;
name of undertakers;
name of reservoir;
situation of reservoir, with sufficient detail to identify it (including the National Grid Reference of the approximate centre of the reservoir);
level above Ordnance Datum to which water may be filled, excluding the allowance made for flood conditions;
level above Ordnance Datum to which water may be stored, excluding the allowance made for flood storage;
date of preliminary or interim certificate as appropriate;
conditions subject to which the reservoir may be filled with water or water may be stored up to the level specified;
date of report, certificate, direction as appropriate;
date of completion of works;
period recommended in the report within which the next inspection should be made;
date of inspecting engineer’s report;
name of inspecting engineer;
name of referee;
address of referee;
date of referee’s decision;
name of person appointing referee;
volume of water that makes a reservoir a large raised reservoir under the 1975 Act.
In these forms of directions, square brackets and the words within them are not to be included where they are inappropriate.
Annotations
Commencement
- I1
Sch. 6 in force at 30.7.2013, see reg. 1(b)