OpenLegislation

The Reservoirs (Scotland) Act 2011 (Commencement No. 3 and Transitional Provisions) Order 2015

S.S.I. 2015/63 · Made 17 February 2015

Original text. legislation.gov.uk does not revise statutory instruments, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Flood Risk Management

Water Supply

Made 17th February 2015

Laid before the Scottish Parliament 19th February 2015

Coming into force 1st April 2015

The Scottish Ministers make the following Order in exercise of the powers conferred by sections 114(2)(a) and 116(1) of the Reservoirs (Scotland) Act 2011f1 and all other powers enabling them to do so.

Annotations to the whole text

Footnotes

f1

2011 asp 9.

Contents

  1. 1Citation, commencement and interpretation
  2. 2Appointed day
  3. 3Transitional provision: information etc. comprising the controlled reservoirs register
  4. 4Transitional provision: information etc. comprising the controlled reservoirs register
  5. 5Transitional provision: information etc. comprising the controlled reservoirs register
  6. 6Transitional provision: information etc. comprising the controlled reservoirs register
  7. 7Transitional provision: modification of section 13 where no preliminary certificate given
  8. Signature
  9. Schedule Provisions coming into force on 1st April 2015
  10. Explanatory note

1Citation, commencement and interpretation

(1)

This Order may be cited as the Reservoirs (Scotland) Act 2011 (Commencement No. 3 and Transitional Provisions) Order 2015 and comes into force on 1st April 2015.

(2)

In this Order—

  • “the Act” means the Reservoirs (Scotland) Act 2011;

  • “the 1975 Act” means the Reservoirs Act 1975f1;

  • “1975 Act reservoir” means—

    1. (a)

      a controlled reservoirf2 which was, immediately before 1st April 2015, required to be registered in a register maintained under section 2(2) of the 1975 Act; or

    2. (b)

      a controlled reservoir which—

      1. (i)

        was not, immediately before 1st April 2015, required to be registered in a register maintained under section 2(2) of the 1975 Act; and

      2. (ii)

        is, on or after that date, required to be registered in a register maintained under section 2(2) of the 1975 Act; and

  • “held”, in relation to SEPA, is to be construed in the same way as “held”, in relation to an authority, in section 3(2) of the Freedom of Information (Scotland) Act 2002f3.

2Appointed day

(1)

Subject to paragraph (2), 1st April 2015 is the day appointed for the coming into force of the provisions of the Act specified in column (1) of the Schedule (the subject matter of which is specified in column (2)).

(2)

Where a purpose is specified in column (3) of the Schedule in relation to any provision, that provision comes into force in accordance with paragraph (1) for that purpose only.

3Transitional provision: information etc. comprising the controlled reservoirs register

Until section 12 of the Act (controlled reservoirs not required to be registered under the 1975 Act) has effect for all purposes, section 9(2) of the Act (controlled reservoirs register) does not have effect in so far as information or a document referred to in section 9(2) relates to a controlled reservoir to which section 12(2) applies.

4Transitional provision: information etc. comprising the controlled reservoirs register

Until section 13 of the Act (structures or areas which become controlled reservoirs after the relevant date) has effect for all purposes, section 9(2) of the Act does not have effect in so far as information or a document referred to in section 9(2) relates to a controlled reservoir to which section 13 applies but which is not a 1975 Act reservoir.

5Transitional provision: information etc. comprising the controlled reservoirs register

(1)

Subject to paragraph (2), until a controlled reservoir is required to be registered under the Act section 9(2) of the Act has effect in relation to the controlled reservoir only in so far as information or a document referred to in section 9(2) is held by SEPA.

(2)

Section 9(2)(h) of the Act (flood maps) has effect in relation to the controlled reservoir only in so far as a map referred to in section 9(2)(h) is held by SEPA on or after 1st October 2015.

6Transitional provision: information etc. comprising the controlled reservoirs register

Until a controlled reservoir is required to be registered under the Act, section 9(4) of the Act (duty of SEPA to arrange for controlled reservoirs register to be available for inspection at all reasonable times) has effect in relation to the reservoir only in so far as information or a document referred to section 9(2) of the Act is held by SEPA on or after 1st October 2015.

7Transitional provision: modification of section 13 where no preliminary certificate given

Where section 13 of the Act has effect in relation to a 1975 Act reservoir, until a preliminary certificate is given under section 37 of the Act in relation to the reservoir, the reference to “preliminary certificate” in section 13 of the Act is to be construed as a reference to a preliminary certificate under section 7(1) of the 1975 Act (certificates of construction engineers).

Signature

AILEEN McLEOD

Authorised to sign by the Scottish Ministers

St Andrew’s House,

Edinburgh

17th February 2015

Provisions coming into force on 1st April 2015

Column (1)

Provisions of the Act

Column (2)

Subject matter

Column (3)

Purpose

Section 4Multiple reservoir managers: supplementary
Section 5(1)Duty of multiple reservoir managers to co-operateOnly for the purpose of bringing into force paragraph (o).
Section 5(2) to (4)Failure of reservoir manager to comply with duty to co-operate
Section 9Controlled reservoirs register
Section 10(1)Reservoir managers’ duty to register with SEPAThe purpose of giving effect to section 10(1) of the Act only in so far as it applies in relation to a 1975 Act reservoir.
Section 11(1) and (2)Controlled reservoirs required to be registered under the 1975 Act
Section 13Structures or areas which become controlled reservoirs after the relevant dateThe purpose of giving effect to section 13 of the Act only in so far as it applies in relation to a 1975 Act reservoir.
Section 15(1) to (3)Registration: supplementaryThe purpose of giving effect to section 15(1) to (3) of the Act only in so far as it applies in relation to a 1975 Act reservoir.
Section 16(2) and (6)Duty of relevant authorities to assist SEPA for specified purposes
Section 17Offences: registrationFor all purposes, except in relation to requirements of section 12(1) of the Act.
Section 27Panels of reservoir engineersIn so far as not already in force.
Section 28(1) to (6)Appointment and removal of panel members
Section 29Dissolution of panels etc.
Section 30(1)Review of decisions to appoint or remove civil engineers from panels etc.
Section 31Consultation with Institution of Civil EngineersIn so far as not already in force.
Section 91(1) and (2)(a) and (l)Powers of entry
Section 92Warrants authorising entry
Section 93(2) to (5)Powers of entry: supplementary
Section 94Offence: preventing or obstructing entry
Section 95(1) to (3)Compensation
Section 96Reports by SEPA to the Scottish Ministers
Section 98(1) and (2)(b)Power of SEPA to require information and assistance
Section 99(1)(b), (2) and (3)Offences: section 98
Section 100Duty to publish guidance on the operation of Part 1 of the Act
Section 106Notices by SEPA
Section 108Civil liability
Section 110(1) and (3) to (9)Crown application
Section 111Offences by bodies corporate

Explanatory note

(This note is not part of the Order)

This Order brings into force on 1st April 2015 the provisions of the Reservoirs (Scotland) Act 2011 (“the 2011 Act”) listed in the Schedule, for all purposes except where otherwise specified. In particular, it brings into force on that date a requirement for each reservoir which is, immediately before 1st April 2015, registered pursuant to section 2(2) of the Reservoirs Act 1975 to also be separately registered with SEPA as a controlled reservoir under the 2011 Act by 1st October 2015.